WEBVTT

00:00.449 --> 00:02.338
My name is Alice Goldbach . I'm a

00:02.338 --> 00:04.449
contracting officers , representative

00:04.449 --> 00:06.449
of the US Army Corps of Engineers ,

00:06.449 --> 00:08.505
Buffalo District . We're here at the

00:08.505 --> 00:08.180
Michigan Pier which is right next to

00:08.189 --> 00:10.133
slip . Three . It's the site of an

00:10.133 --> 00:11.967
ecological restoration project .

00:20.600 --> 00:22.600
So this year's dredging cycle , the

00:22.600 --> 00:24.544
Buffalo River is almost complete .

00:24.544 --> 00:26.711
Roughly 80,000 cubic yards of sediment

00:26.711 --> 00:28.489
from the Buffalo River has been

00:28.489 --> 00:30.544
excavated from the channel sediments

00:30.544 --> 00:32.767
loaded onto scows which are these large

00:32.767 --> 00:35.044
vessels used to transport the material .

00:35.044 --> 00:34.490
The material is then pumped into the

00:34.500 --> 00:36.667
slip behind me which is protected by a

00:36.667 --> 00:38.667
newly installed breakwater designed

00:38.667 --> 00:40.889
with a weir to keep the material in the

00:40.889 --> 00:42.833
slip while allowing fish and other

00:42.833 --> 00:45.056
wildlife to enter and exit . It's going

00:45.056 --> 00:47.167
to take three dredging cycles to fill

00:47.167 --> 00:46.500
the slip with enough sediment to reach

00:46.509 --> 00:48.565
target depths which are necessary to

00:48.565 --> 00:50.490
sustain the aquatic habitat . We

00:50.500 --> 00:52.830
anticipate that about 250 to 300,000

00:52.840 --> 00:54.618
cubic yards of material will be

00:54.618 --> 00:56.729
required . And we're now on the first

00:56.729 --> 00:58.729
dredge cycle of the overall project

00:58.729 --> 00:59.159
which is set to be complete by 2030

