WEBVTT

00:00.009 --> 00:01.898
This is Anthony Perkins . I'm the

00:01.898 --> 00:03.990
operations project manager for the

00:04.000 --> 00:05.833
Black Warrior Tongue , Bigby and

00:05.833 --> 00:08.170
Alabama River Project . Uh Today ,

00:08.180 --> 00:10.199
we're uh here looking at the uh

00:10.210 --> 00:12.720
Demopolis Locking Dam . It's uh had

00:12.729 --> 00:15.229
been down for exactly four months . Uh

00:15.239 --> 00:18.354
The concrete breach uh and concrete

00:18.364 --> 00:21.114
failure occurred . January 16th had the

00:21.125 --> 00:23.665
closure here blocking both the Black

00:23.674 --> 00:25.452
Warrior waterway and the 10 ton

00:25.452 --> 00:27.364
waterways . Well , the event was

00:27.375 --> 00:29.319
actually the concrete failure . Uh

00:29.319 --> 00:32.044
large pieces falling out of the minors

00:32.825 --> 00:35.365
of concrete . The largest piece was 400

00:35.375 --> 00:37.805
tons . So we ended up uh subbing out

00:37.814 --> 00:40.147
the mckinney company out of New Orleans ,

00:40.147 --> 00:42.215
a salvage company that had a 700 ton

00:42.224 --> 00:44.280
crane , one of the largest cranes in

00:44.280 --> 00:46.790
this region uh brought it up and picked

00:46.799 --> 00:49.189
out the larger pieces . Our engineering

00:49.200 --> 00:52.779
came up with systems to dial uh

00:52.849 --> 00:55.729
rods into the existing minor cell , the

00:55.740 --> 00:57.962
floor and the sides of the lock to hold

00:57.970 --> 01:00.450
it and secure it better . We put a lot

01:00.459 --> 01:02.759
of rebar in this concrete . We had

01:02.770 --> 01:06.583
three dive crews that rotated out 24

01:06.593 --> 01:09.273
7 . Initial thoughts were that it could

01:09.282 --> 01:11.953
go into the , you know , June . Uh But

01:11.962 --> 01:14.018
as we were making the last couple of

01:14.018 --> 01:16.063
lifts of concrete . It did end up

01:16.072 --> 01:18.602
curing a little faster uh and reaching

01:18.612 --> 01:21.542
the full strength uh faster than the

01:21.553 --> 01:24.013
previous lift . And also we were

01:24.023 --> 01:25.912
concerned with the water differ ,

01:25.912 --> 01:28.146
temperature , differ from our river

01:28.155 --> 01:30.125
water to the temperature of the

01:30.136 --> 01:32.358
concrete . And we actually reached that

01:32.358 --> 01:34.358
point earlier than expected . So we

01:34.358 --> 01:36.685
were able to open the lock and finish

01:36.695 --> 01:38.917
all the work last week . You know , you

01:38.917 --> 01:40.973
look across the Corps of Engineers .

01:40.973 --> 01:42.973
This is one of the largest concrete

01:42.973 --> 01:44.695
failures that the cor had . So

01:44.695 --> 01:46.639
initially and seeing the amount of

01:46.639 --> 01:49.375
concrete that fell out , uh and what we

01:49.386 --> 01:51.664
had to do what was in front of us . It ,

01:51.664 --> 01:53.775
you know , it looked dawning at times

01:53.775 --> 01:55.775
to , to what we had to do to get it

01:55.775 --> 01:57.775
back open and you and it was at the

01:57.775 --> 01:59.719
worst time of the year in the high

01:59.719 --> 02:02.400
river levels and that to not be able to

02:02.410 --> 02:05.190
fully dewater . The lock was a concern

02:05.199 --> 02:07.940
initially . Uh But , you know , we had

02:07.949 --> 02:10.179
decided to , to get this waterway back

02:10.190 --> 02:12.246
open and the impact it was having on

02:12.246 --> 02:14.468
the users , we had to pour the concrete

02:14.468 --> 02:16.412
underwater and not worry about the

02:16.412 --> 02:18.660
water levels right off the bat . We

02:18.669 --> 02:21.100
involved our nationally , our core

02:21.110 --> 02:23.270
groups are inland design centers ,

02:23.279 --> 02:25.223
engineering . We actually involved

02:25.223 --> 02:27.539
other districts . Uh you know , the

02:27.550 --> 02:30.619
center of expertise . Uh We had uh

02:30.630 --> 02:33.830
within the core , we had some uh folks

02:33.839 --> 02:36.006
and engineers that did have experience

02:36.006 --> 02:38.228
with underwater force . So it was a big

02:38.228 --> 02:40.450
learning experience for not only us out

02:40.450 --> 02:42.561
in the field and repairing , but also

02:42.561 --> 02:45.639
our engineers in our district uh to ,

02:45.649 --> 02:49.360
to get through this and to uh design it

02:49.850 --> 02:51.794
and then see it in action , see it

02:51.794 --> 02:54.679
poured , react to it and the testing

02:54.690 --> 02:56.523
that was involved , it was a big

02:56.523 --> 02:58.800
learning , you know , experience for

02:58.809 --> 03:01.050
all of us and something that will carry

03:01.059 --> 03:03.149
forward and knowing what to look for

03:03.160 --> 03:05.271
and knowing how to make these repairs

03:05.271 --> 03:07.110
in the future if we ever need to .

