^- Hi, Kevin Cannon, Assistant Resident Engineer

00:08.935 --> 00:12.132
^here at the East Branch Dam construction project.

00:12.132 --> 00:15.496
^We're down on the work platform right now.

00:15.496 --> 00:17.658
Quick project update, we've got

00:17.658 --> 00:21.094
about 700 grout holes in the ground so far.

00:21.094 --> 00:25.261
We're getting set up and prepared to start the cut off wall,

00:25.483 --> 00:28.983
hopefully within the next couple of weeks.

00:29.476 --> 00:32.391
You see behind me, they are setting up

00:32.391 --> 00:36.119
for some of the wall equipment at this point.

00:36.119 --> 00:39.174
We anticipate over the course of the next few months

00:39.174 --> 00:42.665
that we'll be well into the cut off wall activities

00:42.665 --> 00:46.832
and slowing down on the drilling and grouting activities.